Skip to content

Pump Station 1 Booster Pump Piping Incident

Unified Command

epa-logo.png dec-logo.png alyeska-pipeline-service-company.png

Whenever there is an incident involving more than one agency with jurisdiction, a joint command arrangement, called the Unified Command is implemented. This webpage provides a compilation of general information, reports, press releases, maps and relevant links meant to aid members of the Unified Command and inform the public during a response. Not all information provided here has been jointly approved or endorsed by every member of the Unified Command.

Location
TAPS Pump Station 1, Prudhoe Bay
Time/Date
8:46 a.m., January 8, 2011
Spill Id
11399900801
Product/ Quantity
The volume of oil released into the building and recovered prior to the January 11 restart is estimated at 1,776 gallons (42.2 barrels). The volume of oil recovered from the building since the January 11 restart is approximately 11,130 gallons (265 barrels). No additional oil has been observed leaking from the pipeline.
Cause
At 8:16 AM, January 8, crude oil was discovered in the booster pump basement at Pump Station 1 of the Trans Alaska Pipeline System (TAPS). The Operations Control Center in Anchorage shut the pipeline down just before 8:50 AM. The leak source appears to be from a below-ground pipe that leads to the basement of the booster pump building. The pipe is encased in concrete. Oil flowed in the small space between the walls of the pipe and the concrete, through the wall of the building into the basement. Alyeska employees and State and federal agencies are jointly responding to the incident. Engineers developed a plan to bypass the affected piping in order to safely restart the pipeline and proceed with repairs to the leak. There are no injuries or apparent impacts to the environment as a result of this incident.

ADEC Situation Reports

Unified Command Press Releases

Fact Sheets

Incident Updates

Click date to show/hide update

January 17, 2011
  • The Trans Alaska Pipeline System resumed operations at 10:18 a.m. Work crews successfully completed the bypass pipeline leading from the booster pump building to the metering building at 3:40 a.m.
  • The reintroduction of crude oil into the pump station piping system began at 5:50 a.m. By 4:00 p.m. the level of throughput in the pipeline had gradually increased to above 500,000 barrels a day, and the flow rate will continue to rise this evening until it reaches normal levels.
  • With the assurance of pipeline flow to Valdez verified, at 2:50 p.m. APSC allowed North Slope producers to return to 100% production levels, after having been restricted to levels as low as 12%. Storage tanks at the pump station reached the 36-foot level before oil began to be reintroduced into the pipeline; the normal maximum operating level is 42 feet.
  • FLIR overflights are planned to continue on a nightly basis.
  • The Unified Command plans to stand down at 6:00 a.m. tomorrow morning, January 18. Alyeska's incident command system will remain in place until crude oil temperatures in the pipeline normalize. At the present time, there are more than 600 people responding to the incident, including 375 people at Pump Station 1.
  • ADEC will assign a project manager to continue to actively manage the state's response and follow-up to this incident until the completion of all necessary oversight and investigation.
January 16, 2011
  • The Trans Alaska Pipeline System resumed operations at 10:18 a.m. Work crews successfully completed the bypass pipeline leading from the booster pump building to the metering building at 3:40 a.m.
  • The reintroduction of crude oil into the pump station piping system began at 5:50 a.m. By 4:00 p.m. the level of throughput in the pipeline had gradually increased to above 500,000 barrels a day, and the flow rate will continue to rise this evening until it reaches normal levels.
  • With the assurance of pipeline flow to Valdez verified, at 2:50 p.m. APSC allowed North Slope producers to return to 100% production levels, after having been restricted to levels as low as 12%. Storage tanks at the pump station reached the 36-foot level before oil began to be reintroduced into the pipeline; the normal maximum operating level is 42 feet.
  • FLIR overflights are planned to continue on a nightly basis.
  • The Unified Command plans to stand down at 6:00 a.m. tomorrow morning, January 18. Alyeska's incident command system will remain in place until crude oil temperatures in the pipeline normalize. At the present time, there are more than 600 people responding to the incident, including 375 people at Pump Station 1.
  • ADEC will assign a project manager to continue to actively manage the state's response and follow-up to this incident until the completion of all necessary oversight and investigation.
January 14, 2011
  • Alyeska Pipeline Service Company (APSC) is in the process of finalizing procedures for shutting down the TAPS and installing a bypass pipeline between booster pump 1 and the TAPS input piping in the metering building at Pump Station 1. The Unified Command has agreed that operation of the TAPS may continue until these preparations are complete.
  • Shutdown is targeted for Friday night, January 14, dependent upon equipment arrival and preparatory progress. APSC estimates the shutdown will last 36 to 48 hours. The first shutdown, following the discovery of the leak, lasted 84 hours.
  • Bypass pipeline materials are being fabricated in Fairbanks and flown to the North Slope for delivery at Pump Station 1. Workers at the pump station have removed snow and placed scaffolding along the bypass pipeline route in preparation for construction.
  • Staging of cold restart equipment is complete at Pump Stations 3 and 5 and continues at other pump stations. ADEC personnel again visited pump stations and valve sites on January 13 to observe cold restart preparations.
  • Following the initial spill cleanup on January 8, responders constructed a temporary containment tank in the basement of the booster pump building to collect leaking oil at the seep site. With the temporary TAPS restart shortly after 9:00 PM on January 11 (see Sitrep #4), oil began flowing again through the suspect booster pump discharge piping. Flow from the seep has appeared to remain steady since the restart, with response crews recovering approximately 11, 214 gallons (267 barrels) of oil from the tank, which will be re-injected into the TAPS line at a later date.
  • At the time of the leak detection, two pipeline inspection/cleaning gauges (PIGs) were making their way down the pipeline. The restart of oil flow on January 11 has allowed the PIGs to move down the pipeline to locations suitable for their sequester: one at Pump Station 8; the other at the Valdez terminal. The oil in the pipeline cooled down during the 84-hour flow stoppage, and capturing the PIGs ensures that they cannot push along any subsequent ice or wax buildup, which could damage pump station equipment.
  • Airborne crews have made several overflights of the entire pipeline with forward-looking infrared (FLIR) imaging equipment to look for thermal evidence of oil leaks; no actual or potential leak sites have been identified.
  • More than 550 people across the state, including those from industry and federal and state agencies, are involved in the response to this incident. APSC will continue to prepare for the planned TAPS shutdown and for the contingency of a cold restart thereafter. Personnel will maintain oil recovery from the booster pump. Monitoring of soil gas probes around the booster pump building will be included in spill detection efforts as activity around the building permits.
Incident Location

Contact Information

Aerial view: TAPS Pump Stn 1

Maps

Photos

Images may be downloaded for free and used in publications provided credit is given to the source.

January 12, 2011

January 13, 2011

January 14, 2011

January 15, 2011

external link indicator Indicates an external site.